Nice Wolf battles coastal storms to build steps.

Installing step pavers.

Slow work on steps

It’s bloody freezing outside.  I’m sure our weekend weather comes from the Antarctic.  (I’ve not had a winter for several years, so I may be a little sensitive.)  The Nice Wolf is tough!  And handy.  And is currently outside working on step pavers and cobblestones through squalls of rain and chilling wind.

He’s on a schedule.  The professional landscapers are yet to install our garden lights and the roller door which covers some outdoor storage beside the canal.  To complete these two jobs, they need us to complete the step paving which houses step light canisters and the section of cobblestone paving around the storage area.  Of course, by “us”, I really mean The Nice Wolf.  These are both seriously slow jobs.  The steps have to be done step by step, literally.  There is concrete carting and setting time involved and some fiddly circular holes to be made for the light canisters.  Perhaps a professional might knock the job off in a day, but for my weekend warrior, it is taking more than a few weekends.  Never-the-less, he’s getting there and his labour is free.

Laying cobblestones.

Cobblestone progress.

The landscaping is slowly progressing.  The outdoor tiles around the pool area have been completed and we have a fence and gate installed to restrict access from our front yard.

Monument colorbond fence.

Colorbond pool fence.

We went for a cheap option for this side of the pool fence.  We may alter this area to include a covered outdoor kitchen a few years down the track, in which case, the fence will go.  In the meantime, I’ll cover it up with some creepers on the poolside.

I’ve been itching to get started on the planting.  I need to be patient and wait for the hardscaping to be done.  The longer I have to wait, the more I change my mind.  I’m oscillating between choosing a frangipani or an olive tree as our feature tree.  On one hand I love the colour of the olive leaves for our colour scheme, on the other hand, the frangipani’s sculptural trunk and branches are hard to beat.

Coastal garden

Lomandra, coastal banksia and a native ground cover.

I snuck in a few extra plants which made me very happy.  What can be better than gardening beside the water?  My coastal banksias were looking lonely, so I planted a row of lomandra and a row of native ground cover either side of the trees.  I popped in a few ground cover plants around my kangaroo paws too, to create a bit of interest and try to limit weed growth.

Six months maintenance.

Six months since handover past and I sent my list of items requiring attention to the builder.  There was nothing of great significance on the list and I’m pleased to report that most of the items were quickly fixed with a minimum of fuss and tradie visits involved.  I will do a full review of our builders, Webb and Brown-Neaves, sometime soon, but I must give them a pat on the back at this point for making the “six-month maintenance stage” fairly painless.

Ensuite.

Our ensuite. Simple, spacious and lovely!

Finally, a little “HELLO” to the House By The Water tourists!   We’ve been getting people stopping in their cars outside our house to take photos.  Some are braver than others and say “hi”.  I love that one lady this week asked if she could hold her tile (that she happened to have in the car) up against our paintwork.  That’s totally something that I would have done!

4 thoughts on “Nice Wolf battles coastal storms to build steps.

  1. trixee says:

    I can relate to changing minds the more the landscaping gets delayed! Your sneaky plantings look lovely though. The cobblestones are looking awesome, I’m so impressed with Nice Wolf’s patience and cold weather tolerance. Glad your 6 months maintenance went well.

  2. Our beautiful farm is sold to a very appreciative young couple who will love it and we have moved on to our next project…which brings me to Igor and his amazing cobble stone skills. Thought you might like a ‘holiday’ and have a play with our new drive. It will be 84 metres long. Cobblestones? Maybe not. At this stage the local earthmover and his bulldozer are booked in and a couple of truckloads of gravel should do the job. Ps Snow on Bogong Igor.

Leave a reply to trixee Cancel reply